Work on the Bni Azimane dam in Driouch province has reached 98 %, at a total cost of about 1.4 billion dirhams.
Located on the Oued Kert in Tleta Azlaf commune, some 25 kilometres from Driouch, the structure began filling its reservoir last May.
Its storage capacity is 44 million cubic metres and its height about 70 metres above the foundations, with a mixed design combining roller-compacted concrete and compacted earth.
The project aims to strengthen drinking water supply for nearby douars, farm irrigation and livestock watering, while protecting Mezghitane and downstream areas from floods.
The site has generated more than 600,000 workdays since October 2021, under the national water programme 2020-2027, with completion expected in December 2026.
Related news
More in Driouch
Driouch-Guercif highway nears link to Nador West Med port
The motorway project linking Driouch to Guercif is entering a decisive phase, with work on its third section more than 95 % complete. The…

Driouch-Guercif motorway passes 95% completion
Work on the motorway linking Driouch to Guercif has passed 95 % completion, bringing the project close to finishing. The infrastructure is…

Fatal Jaadar Crash Revives Road Safety Debate in Azghanghan
The death of a motorcyclist in Jaadar, near Azghanghan, has reopened the debate over the dangers of the main road in the area. The Nador…
Comments (0)